Orange Zone Water Line Construction

Updates

None at this time.

Schedule

Task Name Start* Finish*
Erosion & soil control Wed 3/15/2017 Fri 3/17/2017
Mobilize equipment & materials Mon 3/20/2017 Wed 3/22/2017
Directional drilling Wed 3/22/2017 Tue 4/4/2017
Water line installation through Golf Course Wed 4/5/2017 Thu 4/20/2017
Indian Peaks Trail road crossing Tue 4/18/2017 Thu 4/20/2017
Water line testing Fri 4/21/2017 Wed 4/26/2017
Water line installation Fri 4/21/2017 Wed 4/26/2017
Water line testing Thu 4/27/2017 Tue 5/2/2017
Restoration, clean-up & demobilization Wed 5/3/2017 Fri 5/5/2017
**Schedule subject to change
‚Äč**All work is weather-permitting